Metropolitan Branch Trail Projected Design and Construction Schedules


Phase A - John McCormack to Bates Road
Design - October 2017 to August 2018
Construction - August 2018 to November 2018
 
Phase B - Gallatin Street to First Place
Design - October 2017 to December 2018
Construction - December 2018 to September 2019
 
Phases C and D - First Place to Bates Road
Design - October 2017 to January 2018
Construction - January 2018 to January 2020
 
Actual schedule of completion for each phase will vary based upon several factors including, but not limited to weather conditions, size and degree of difficulty of the area, material and contractor availability, crew sizes, and complexity of the changes that may be inevitable after construction has already begun.