two week look ahead

 


Current Two Week Look Ahead Schedule

11/13/18 - 11/27/18

  • Design

    • Review and address NPS comments on Submittal B

    • Resolve outstanding ADA ramp design in the SE corner of 1st Place NE and Entrance to WMATA Parking lot.

    • Finalizing permit applications for Phase D and submitting them to WMATA and NPS

    • Developing materials for the Schools for MOT in phase B

  •  Construction

    • Installing catch basin on Stage 2 Phase A, weather pending

 


Past Two Week Look Ahead Schedules

10/16/18 - 10/29/18

  • Design

    • Submit 90% plans for Submittal D to DDOT and DOEE

    • Finalize permit applications and submit Phase D to WMATA and NPS based on the 90% submittal

  • Construction

    • Excavation and Stone placement for Stage 1 of Phase A

    • Placement of underdrain in the stone for Stage 1 of Phase A

    • Placement of Asphalt on Stage 1 of Phase A

    • Excavation and Stone placement for Stage 2 of Phase A

    • Placement of underdrain in the stone for Stage 2 of Phase A

    • Drainage Installation Stage 2 of Phase A

10/2/18 to 10/15/18

  • Design

    • Submit 90% plans for Submittal D to DDOT and DOEE

    • Finalize permit applications and submit Phase B and D to WMATA and NPS based on the 90% submittal

  • Construction

    • Excavation and Stone placement for Stage 1 of the trail

    • Placement of underdrain in the stone

    • Placement of Asphalt on Stage 1

9/18/18 - 10/1/18

  • Design

    • Submit 90% plans for Submittal B to DDOT and DOEE

    • Finalizing 90% plans for Submittal D to DDOT and DOEE

    • Finalizing Submittal D 90% plans to WMATA,

    • Finalize permit applications and submit Phase B and D to WMATA and NPS based on the 90% submittal

  • Construction

    • Excavation and Stone placement for Stage 1 of the trail

    • Placement of underdrain in the stone

    • Placement of Asphalt on Stage 1

9/5/18 to 9/18/18

  • Design

    • Submit 90% plans for Submittal B to DDOT and DOEE

    • Finalize 90% plans for Submittal D

    • Submit 90% plans for Submittal D to DDOT and DOEE

    • Finalizing submittal of Submittal B and D to WMATA, 90% plans

    • Finalize permit applications and submit them to WMATA and NPS based on the 90% submittal

  • Construction

    • Excavation and Stone placement for Stage 1 of the trail

    • Placement of underdrain in the stone

    • Placement of Asphalt on Stage 1

8/21/18 to 9/04/18

  • Design

    • Finalizing resubmittal for Submittal B and D to DDOT, WMATA, and DOEE 90% plans

    • preparing permit applications and submitting them to WMATA and NPS based on the 90% submittal

  • Construction

    • Completion of Erosion Control Installation

    • Completion MOT Installation (Construction sign installation, and new stop Bars at the John McCormack and Bates intersection)

    • Excavation and Stone placement for Stage 1 of the trail

    • Placement of underdrain in the stone

8/7/18 to 8/20/18

  • Design

    • Submit Phase “B” 90% plans

    • Addressing Comments on Phase “B” and “D” from DOEE and DDOT

  • Construction (Once plans are accepted Phase “A”)

    • Erosion Control Installation

    • MOT Installation (Construction sign installation, and new stop Bars at the John McCormack and Bates intersection)

    • Excavation and Stone placement for Stage 1 of the trail

    • Placement of underdrain in the stone

7/24/18 to 8/6/18                                                                      

  • Preparation of final construction package for Submittal A.

  • Addressing Comments on Phase B and D

  • Geotechnical analysis on soil and foundation borings.

  • Evaluation/revisions to design (Submittal B and D), and structural design/calculations (Submittal D) based on the results of geotechnical analysis.

7/3/18 to 7/16/18

  • Participate in coordination of meetings with DDOT, DPW, and DC Bilingual School.

  • Participate in pre-construction meeting for Submittal A.

  • Address revisions to MOT plans as a result of MOT meeting with DDOT and DPW.

  • Prepare final construction package for Submittal A.

  • Perform geotechnical analysis on soil and foundation borings.

  • Conduct evaluation/revisions to design (Submittal B and D) and structural design/calculations (Submittal D) based on the results of geotechnical analysis.

6/26/18 to 7/9/18

  • Performed drilling operations.

  • Performed geotechnical testing/design.

  • Based on the results of geotechnical testing and infiltration testing, provided updates to design on submittal B and D.

  • Coordinated with DOEE on approvals for Submittal A and reviews for Submittals B and D.


6/13/18 to 6/25/18

  • Addressed comments on Submittal A and resubmittal to DDOT. Comments expected from DDOT this week.

  • Addressed comments on Submittals D.

  • Coordinated utility marking and drilling operations.

  • Performed drilling operations.

  • Coordinated with DOEE approvals for Submittal A and reviews for Submittals B and D.


5/29/18 to 6/12/18

  • Performed drilling operations.

  • Addressed comments on Submittals B and D.

  • Coordinated with CSX and WMATA for soil boring operation requirements.